The phrase,'Unsound Transit', was coined by the Wall Street Journal to describe Seattle where,"Light Rail Madness eats billions that could otherwise be devoted to truly efficient transportation technologies." The Puget Sound's traffic congestion is a growing cancer on the region's prosperity. This website, captures news and expert opinion about ways to address the crisis. This is not a blog, but a knowledge base, which collects the best articles and presents them in a searchable format. My goal is to arm residents with knowledge so they can champion fact-based, rather than emotional, solutions.

Transportation

Showing posts with label 4.31 Seattle Bus Tunnel. Show all posts
Showing posts with label 4.31 Seattle Bus Tunnel. Show all posts

Monday, March 10, 2008

King County Metro FAQ

1/15/08
Metro Transit, or Metro for short, is the public transit authority of King County, Washington, a division of the King County Department of Transportation. It began operations on January 1, 1973, but can trace its roots to Seattle Transit, founded in 1939, and Overlake Transit Service, founded in 1927. As of 2004, it operated 1,363 buses on 235 routes. Its annual ridership in 2003 was 100 million, making it the ninth largest bus operator in the nation

History

Metro was established in 1972 as a combination of Seattle Transit and suburban authorities. The agency was independent until 1994, when a popular vote merged it with King County government. In 1968, 1970, and 1995, voters rejected heavy or light rail systems. Today, Metro operates bus service in partnership with Sound Transit, which was established by a 1996 vote to provide regional bus and rail service. Both the 1995 and 1996 measures were a result of the Regional Transit Authority, now popularly known as Sound Transit.

Metro Buses in Seattle, Washington


Operations

Routes

Metro and four other transit organizations in the Puget Sound region use the same type of monthly passes, which can be issued in various configurations.

Metro and four other transit organizations in the Puget Sound region use the same type of monthly passes, which can be issued in various configurations.

Metro combines service patterns typical of city and suburban bus networks. The city network, descended in large part from the Seattle Transit system of converted streetcar routes, is arranged in a hub-and-spoke pattern centered on downtown Seattle, with lesser amounts of crosstown service. Routes in the city network are numbered from 1 to 79, with special late-night "Owl" routes in the 80s and the waterfront streetcar and its replacement coach numbered 99. Because of the scattershot evolution of the system, there is no easily discernible pattern to the route numbers, although there are clusters in certain neighborhoods: for example, the 65, 66, 67, 68, 70, 71, 72, 73, 74, 75, and 79 all run through the University District.

The in-city routes with the highest ridership are the 7, traveling from downtown Seattle through the International District and Rainier Valley; the 36, traveling from downtown Seattle through the International District to Beacon Hill; the 43 and 49 (the latter of which was formerly the northern portion of route 7), traveling through Capitol Hill to the University District; the 44, a crosstown route connecting the University District and Ballard; the 48, a very long crosstown route connecting most parts of east and north Seattle to the Central District and Rainier Beach, and the 3 and 4, connecting downtown to Queen Anne, First Hill, the Central District, and Madrona. However, because of the bus-only nature of the system, there are many other heavily used routes.

The suburban system is more numerically organized. Roughly speaking, areas south of the city from Burien and Des Moines through Renton and Maple Valley are served by routes numbered from 101 to 197. Areas east of the city from Renton to Bothell are served by routes numbered from 200 to 291. Areas north of the city from Bothell to Shoreline are served by routes numbered from 301 to 373. Numbers in the 400s and, for the most part, the 800s, are reserved for Community Transit (Snohomish County) commuter routes serving Seattle; numbers in the 500s are used by Sound Transit's Regional Express system, save for Pierce Transit's routes 500 (Federal Way-Tacoma) and 501 (Federal Way-Milton-Tacoma). 600 series routes are general "express" routes that are used for special purposes (the 630, for example, is intended to service the Kingsgate Park and Ride from Bellevue until construction adjacent to the park and ride is complete)as well as the Olympia Express Lines operated by Pierce Transit and Intercity Transit, and 900 series routes are reserved for Dial-a-Ride services and for routes serving outlying areas such as Duvall and Carnation.

Special routes numbered 206-208 and 885-890 are used by Metro to serve Bellevue School District students and special coaches are dispatched around the region to serve as special shuttles for local events, including Seattle Mariners baseball games, Seattle Seahawks football games, and other special events.

Major all-day Metro routes in the suburbs include the 120, connecting Seattle and Burien; the 174 and 194, connecting Seattle, Sea-Tac Airport, and Federal Way; the 150, connecting Seattle, Southcenter and Kent (The Kent to Auburn portion was replaced by the new route 180); the 101 and 106 between Seattle and Renton; the 255, connecting Seattle and Kirkland; the 240, connecting Renton and Bellevue; the 230 and 253, connecting Bellevue, Crossroads, and Redmond; the 271, connecting Issaquah, Bellevue, and the University District; the 347 and 348, connecting Northgate and North City; and the 358, operating up Aurora Avenue N. to Shoreline.

Ride Free Zone

To reduce delays, a portion of downtown Seattle is a ride free zone, where fares are not collected between 6 a.m. and 7 p.m. The ride free area extends from the north at Battery St. to S. Jackson St. on the south, and east at 6th Avenue to the waterfront on the west. The waterfront streetcar (Metro Route 99) and Metro routes 116, 118 and 119 are not included in the Ride Free area. Between 7 PM and 6 AM, bicycles are only allowed to be loaded or unloaded at a route's first and last ride free stop. This is a safety policy to reduce the potential of too many cyclists being between buses in heavy downtown traffic.

Metro Bases

Trolley buses parked at Metro Transit's Atlantic Base on Easter Day, 2007

Trolley buses parked at Metro Transit's Atlantic Base on Easter Day, 2007

Metro operates out of seven bases spread throughout its 2,134-square-mile operating area: Atlantic, Ryerson, Central (1333 Airport Way S, Seattle), East (1975 124 Ave NE, Bellevue), Bellevue, South (12100 E. Marginal Way S, Tukwila), and North. Atlantic, Central, and Ryerson Bases are located close together near Safeco Field south of downtown Seattle. East and Bellevue bases are located in north Bellevue. South Base is in Tukwila; the innovative North Base, built mostly underground in 1989, is in Shoreline. The South and East transit facilities finished an ADA retrofit in 2001. Atlantic Base is unique in that it only serves ETBs. South Base is the largest base, with over 500 operators. South Base is located across the street from the Training Center, a facility where operator training, new equipment qualifications, and retraining take place. Bus Tunnel

A major Metro operations facility is the Downtown Seattle Transit Tunnel, or DSTT. The DSTT, a 1.3-mile-long, five-station tunnel through the center of downtown Seattle, was completed in 1990 at a cost of $444 million. Planned from the outset to be convertible to light rail operation, the tunnel was outfitted with rails and overhead trolley wire. A fleet of 235 dual-propulsion buses were produced by Breda of Italy, powered by electric traction in the tunnel, and diesel on city streets. Mode changes occurred at the north and south portals. The tunnel suffered some significant problems in operation, as the Breda buses proved overweight and unreliable. The original plan to have up to 600 dual-powered buses using the tunnel never materialized; the 235 Breda buses were the primary buses to use the tunnel until Metro acquired its hybrid fleet in 2005. The tunnel was closed in 2005 to replace the rails, lower the track bed for modern ADA-compliant light rail cars, and complete a stub tunnel for a future LINK light rail extension to the north. The tunnel finished its retrofit and returned to service on September 24, 2007. The tunnel is served by routes 41, 71, 72, 73, 74, 101, 106, 150, 174, 194, 212, 217, 225, 229, 255, 256, 301, and 550. Several routes that formerly served the tunnel will remain on surface streets including the 177, 190, 196, 266, 306, and 312. Reasons for the changes to tunnel routes include the lower bus volumes possible in the tunnel due to light rail service and a desire to increase the number of trips serving the tunnel in the midday hours


Projects

Significant projects include a regional smart card initiative, and the exploration of Bus rapid transit or BRT in several corridors throughout the county.

Introduced in April 2006 was Metro's proposed "Transit Now" initiative which was approved by the voters of King county later that year. The initiative will increase Metro's bus service by 20 percent over the next ten years through the addition of a one-tenth percent sales tax increase. The proposal focuses on establishing improving current service, adding service to the county's growing outlying regions, service partnerships with large employers, and the establishment of 5 BRT corridors dubbed "Rapid Ride," as follows:

  1. Aurora Avenue North. This line would run from King Street Station downtown to the Aurora Transit Center in Shoreline
  2. West Seattle. The line would run from West Seattle over the West Seattle Bridge, the SODO Busway and into Downtown through the Transit Tunnel, potentially reaching the University of Washington in the future.
  3. Ballard. The line would also run from King Street Station to Ballard via 15th Ave. West and Elliot Ave. West.
  4. Bellevue to Redmond.
  5. Federal Way to Sea-Tac. This line would connect with Sound Transit Central Link light rail beginning in 2009.

All lines would use new, low-floor, branded buses to set them off from traditional routes. Stops would be combined to increase speed and reliability and create "stations" more akin to what is found on rapid transit lines. Some form of off-bus fare collection would be considered.

Information technology

Collaborating with several local jurisdictions, Metro was also an early experimenter with transit signal priority (TSP), a system to extend green lights to allow buses to get through. The system can boost average speeds as much as 10%, and is in use on several of the city's busiest corridors, including Aurora Avenue N., Rainier Avenue S., and Lake City Way N.E. Metro lacks a smart card fare collection and automated stop announcements.In 1998 the fleet was updated with a Automatic Vehicle Location (AVL) system that utilizes battery-powered beacons located at some stops. Metro is currently in the process of replacing the system as part of a system-wide radio update.Metro does use Traffic Signal Priority along some major arterials, utilizing a specialized radio system.The extent of Metro's intelligent transportation systems (ITS) available for customers has been limited to two projects: an early project by the University of Washington utilized the tracking data to provide real-time bus information. This is now hosted by Metro under the name Tracker. Google Maps now provides more extensive trip planning using schedule data as part of their Google Transit service.A pilot project provided bus information displays along a city arterial. Metro discontinued the project in 2005, citing the cost of maintenance and technical problems.

Fleet

Metro operates one of the largest bus-only fleets in the country (discounting its short waterfront streetcar, which is temporarily out of service). Bus-only operation results in some interesting operating characteristics of the Metro fleet, most notably a high concentration of articulated buses—over a third of the total and the largest articulated fleet in North America. Metro's use of articulated coaches dates back to 1978, when it was the first large agency in the country to adopt the technology. The other two-thirds are made up of mostly Gillig Phantom coaches: 395 40-foot (3200-3594), 15 35-foot (3185-3199; the latter two, 3198 and 3199, are used for special/disabled services), and 95 30-foot (1100-1194) buses. The 100 low-floor 40 foots (3600-3699) were built by New Flyer and are used mostly on routes within the Seattle city limits.

A Gillig Phantom trolley in Seattle.

A Gillig Phantom trolley in Seattle.

Metro also maintains a large fleet of electric trolley buses (ETBs). The ETBs prove useful both as zero-emission vehicles, and as vehicles well adapted to Seattle's hilly terrain. Until 2005, this was the largest ETB fleet in the country, including 236 dual-mode Breda "tunnel buses." In 2002, Metro replaced its 100 AMG trolleys with new Gillig Phantom shells. The drive train of the AMG coaches was retained with new electronics, saving approximately $200,000 per coach. Metro is now rebuilding 59 of the now retired Breda dual-mode coaches, converting them to electric-only operation and refurbishing them to replace aging MAN articulated ETBs. The rebuild includes new Kiepe current collection equipment, new interior upholstery, a completely new driver's compartment, and new ADA-compliant signage.

The agency pioneered technologies in widespread use today. In 1979, the AMG trolleys were ordered with some of the first wheelchair lifts in the nation, promising a completely new level of independence for disabled residents. Early lifts were severely flawed, but by the mid 1980s the lifts were generally reliable and were ordered on all new buses. With the retirement of the 1400-series buses in 1999, the entire fleet became wheelchair-accessible—again, the first fleet its size to do so. Strangely, the agency was reluctant to adopt low-floor buses, not buying any until 2003.

Metro operates the largest fleet of articulated hybrid buses in the country, the fleet of 214 New Flyer DE60LFs it purchased to replace the Bredas. (Sound Transit bought an additional 21 similar buses.) Metro's hybrids were purchased to run in the Downtown Seattle Transit Tunnel, where they will operate together with light rail vehicles beginning in 2009. In the tunnel, the hybrid buses use electric traction to 15 mph; after 15 mph, traction is a combination of electric and diesel, operating in a quieter, low-emission mode. On May 16, 2007, Metro awarded its biggest contract ever to New Flyer for the purchase of 715 more 60-foot hybrid buses.[4]

The National Renewable Energy Laboratory (NREL) conducted a one-year comparative study between conventional diesel and GM hybrid-powered buses operating on a typical King County drive cycle. Results showed that the GM-hybrid powered buses lowered fuel consumption by 23%; NOxby 18%; carbon monoxide (CO) by 60%; and total hydrocarbon (THC) by 56% when compared to conventional diesel buses.

In addition, like Golden Gate Transit and SamTrans in the Bay Area of California (and unlike most transit agencies), almost all of Metro's fleet has highback non-reclining seating as opposed to lowback seating that is used by most other transit agencies on local routes. These buses operate on both local and express routes.


Source Wiki

Sound Transit misstates Seattle Transit Tunnel numbers

Emory Bundy Letter Re: "He Said She Said" Reporting:
Seattle Light Rail


By Emory Bundy (2001.08.29)

Erica, as one who long lamented the inattention of the press to one of the largest public works project in our history, Link light rail, putatively addressing our leading urban challenge, I am grateful for the attention you have given the downtown tunnel. It exceeds that of your peers, and, for that, deserves commendation.

I respectfully object, however, to the following sentence and premise: "As usual, it's all in how you massage the numbers." You imply that Sound Transit and its critics each simply have a point of view, and that both sides work to manipulate data to prove their point. How even-handed of you.

As a manager and producer at KING, I formed a negative opinion of "he says/she says" reporting, in which both sides are considered equally reliable, or equally unreliable, get their counterpoint say, and that's the story. The reporter takes no responsibility to actually pursue and report on what the truth is, or at least some serious effort to approximate it. It's a lot easier to do that kind of a superficial job. It serves, not the public interest, but the comfortable interests of established power--particularly power that has immense resources to create, propagate, and spin its own messages, while plain citizens must rely on the diligence of the press.

Those of us who are alarmed about Sound Transit are desperate for journals and individual reporters who are diligent, and willing to pursue and report the facts. We welcome your scrutiny. But don't make facile assumptions that, because we've formed a point of view, it must be self-serving. Or that, because it has immense power and lots of money, Sound Transit is reliable.

Sure, last September 88 of us, from all walks of life and corners of the community, pleaded for an independent audit of Sound Transit, and said we feared the light rail project was at least a half-billion dollars over it's already-admitted quarter-billion dollar cost overrun. (The Sound Transit claim at that time was $1.9 billion [$1995]; the original projection was $1.67 billion.) We had and specified a credible basis for our suspicions, including work recently concluded by the Washington Research Council that seemed, and proved to be, very conservative.

Well, we got the back of the hand, with Ron Sims and Dave Earling leading the assault, which was generously reported by the daily newspapers. Earling pronounced Sound Transit had already been "audited to death," and that there were no cost overruns. He invoked an audit performed by Deloitte Touche to prove his point. (The firm's work is so satisfactory to the preferences of Sound Transit that recently it was awarded another, large contract.) He accused us of twisting the truth.

I supposed you can just take that as Sound Transit's massaging of the data, vs. ours, in the matter of cost overruns--as you have in this instance of the latest Sound Transit tunnel study vs. that of Integrated Transport Research. Everybody's got their own numbers, and some kind of self-interest to pursue, you aver. But I urge you to consider probing your assumptions, and suggest there are underlying facts that merit surfacing, without fear or favor. Reporting with the premise that Roger Pence, and an estimable figure like Jim MacIsaac, of ITR, are equals, in professional experience, expertise, or integrity, and should be considered equally reliable sources, is tragically misguided.

But don't take my word for it. Check it out.

Thursday, February 28, 2008

KingCo Metro fires 8 guards with criminal records

KingCo Metro fires 8 guards with criminal records

King County Metro fired eight private security guards for the Seattle bus tunnel after the sheriff's office discovered they had criminal records.

The records came to light after one guard filed a police report in which she was the victim.

King County sheriff's spokesman John Urquhart (URK'-hart) says that turned up an arrest warrant on a drug offense, prompting the broader review. Another guard was wanted for domestic violence and six others had misdemeanor convictions.

The sheriff's office runs a transit police unit, which has two commissioned officers in the tunnel. Metro also hires two private guards for each bus tunnel station.

Private security guards are allowed to work 60 days on a temporary permit while their background is checked.

___

Thursday, February 21, 2008

Citizens Panel worried about Sound Transit's Rising Costs

Citizens’ Year-End 2007

Performance Report on Sound Transit



February 21, 2008
Dick Chapin
Sound Transit Board
Honorable Greg Nickels, Chair
Union Station
401 South Jackson Street
Seattle, WA 98104
Dear Chair Nickels and Board Members:

We are happy to report that on balance Sound Transit’s progress in delivering the regional transit system was good in 2007. On the other hand, we continue to have areas of concern that we believe require close monitoring to prevent them from becoming problems.

The progress is summarized below.
Capital Projects Moving Forward. There was visible progress along the entire Central Link alignment, including in the design and planning of the next stages of the regional light rail system, University Link and East Link. Regional Express capital projects opened for service on I-405 at Canyon Park in Bothell and at Totem Lake in Kirkland. Five additional projects were under construction. Sounder projects at Mukilteo and Lakewood Stations were in construction, as was continuing work on track and signal improvements to add capacity to the
commuter rail system.

Ridership Growth. Service was added on ST Express bus and Sounder, resulting in increased ridership of 27% on Sounder and 10% on Express bus, both exceeding expectations for the year.

State of the Agency. Positive reports from federal oversight, state and financial compliance audits and a performance audit of Link testified to the soundness and strong management of the agency. These reviews demonstrate that despite numerous challenges that the agency faced, this is a mature, effective organization with an accumulation of knowledge and skills that greatly benefit our region.

While there is much good news to report, there were challenges and disappointments as well.

Failure of Proposition 1. The biggest setback in 2007 was the failure of voters to approve Proposition 1. In hindsight, the defeat is attributable to many factors including the overall size of the combined roads and transit measure, difficulty in explaining the costs of the combined measure, and still diminished (but rebounding) credibility that lingers from the problems the agency faced in 2000-2001. We applaud the agency’s willingness to incorporate these lessons learned into a serious investigation of a reconstituted proposal for system expansion that could be presented to voters either this fall, or in the fall of 2010.
Construction and Planning Environment. The continuing tight construction
market in the region, third party funding shortfalls, scoping and siting
disagreements, and property disputes all took their toll on schedules and budgets
in 2007.

Need to Improve Access to Transit Services. As ridership has steadily grown
on Sounder and ST Express, some routes are reaching capacity constraints. ST
Express has all of its buses in use and cannot add significant new service. The
Sounder south corridor has developed access issues at its stations in Sumner,
Puyallup and Auburn where either new parking capacity, local feeder service or
both are needed. These issues highlight the need for regional cooperation among
Sound Transit and other agencies on sensitive policy issues affecting cost-
effectiveness in use of resources and who pays for which services.
Transit Operating Costs. Our previously expressed concerns continue on the
growth in operating costs of Sound Transit’s bus service, and are joined this year by a concern about a rise in the costs of Tacoma Link. ST Express and Tacoma Link total costs both grew 10% in 2007. These growth rates are unsustainable
when compared to the 5% cost growth that Sound Transit continues to assume for future year planning purposes.

Transition from Capital to Operations. Over the years, COP has highlighted the need for improvement in various areas. As the agency draws closer to
beginning service for Central Link, we would draw the Board’s attention to an area that is fraught with potential for surprises: the transition from capital project to operations. We are concerned about the complexity of coordination created by the fact that operation is not entirely in Sound Transit’s control.
These challenges do not detract from the successes. Sound Transit is a thriving organization with strong leadership and management. We urge you to be diligent in oversight of the weakest areas, as we promise to be as well.

Sincerely,
CITIZEN OVERSIGHT PANEL


Richard U. Chapin
Chair

Cc: Joni Earl

Introduction
The Sound Transit Citizen Oversight Panel (COP) is a 15-member volunteer body appointed by the Sound Transit Board to oversee and monitor the implementation of Sound Move, the voter approved regional transit plan. The Panel communicates to the Board periodically as issues arise. In addition, it has prepared progress reports since the program’s inception. This is the Panel’s nineteenth report and covers Sound Transit’s performance during 2007.

Summary of Sound Transit Performance in 2007


Accomplishments
Sound Transit’s progress in delivering the regional transit system was good in 2007. The agency met 36 of the 43 milestones it set at the beginning of the year. Despite numerous challenges the agency faced, Sound Transit continued to demonstrate that it is a mature, effective organization with an accumulation of knowledge and skills that greatly benefit our region.

Capital Projects Moving Forward. Most prominently, there was visible progress along the
entire Central Link alignment. The surface street disruptions on Pine Street downtown and along
Martin Luther King Way South were replaced by new pavement, plantings and artwork.
Trackwork and stations began to appear in the Rainier Valley corridor. Elevated guideways
along I-5 emerged from fenced construction sites and stations began to rise at McClellan Street
in South Seattle and International Boulevard in Tukwila. The Downtown Seattle Transit Tunnel
reopened on time to the public and to bus travel. Construction was very much in evidence at the
airport. The Central Link Initial Segment is now 85% complete and on schedule to open for
service in July 2009. The next stages of the regional light rail system, University Link and East Link, continue to make good progress in the design and planning stages respectively.

Regional Express capital projects opened for service on I-405 at Canyon Park in Bothell and at Totem Lake in Kirkland. Additional projects were under construction in South Everett, at the Bothell Branch Campus, on Mercer Island, on I-90 in Bellevue, and in Issaquah. Ten additional projects throughout Snohomish and East King Counties are under development by localjurisdictions with significant funding contributions by Sound Transit.

Sounder projects at Mukilteo Station in Snohomish County, and at South Tacoma and Lakewood Stations in Pierce County were in construction, as was continuing work on track and signal
improvements to add capacity to the commuter rail system.

Ridership Growth. 2007 saw added service to ST Express bus and Sounder commuter rail and the significant increases in ridership that resulted. Ridership was up 27% on Sounder and 10% on ST Express, both exceeding expectations.

Challenges and Issues


Failure of Proposition 1. The biggest setback in 2007 was the defeat of Proposition 1. The
Legislature’s decision to yoke the transit and the roads plans into a single ballot resulted in a
whole that was not compelling to voters. While hindsight is always 20/20, and obviously many
factors were involved, including the overall size of the combined roads and transit measure,
difficulty in explaining the costs of the combined measure, and still diminished (but rebounding) credibility that lingers from the problems the agency faced in 2000-2001. We applaud the agency’s professionalism in moving forward and willingness to incorporate lessons learned from the voters as it considers new options for system expansion. We hope any modified ST2 plan that is adopted will make a stronger effort to communicate to the public the cost effectiveness of its individual elements and the environmental benefits of regional transit overall. Need to Improve Access to Transit Services. As ridership has steadily grown on Sounder and ST Express, some routes are reaching capacity constraints. ST Express has all of its buses in use and cannot add significant new service until new buses and the related maintenance base capacity are acquired. Access issues have developed in the Sounder south corridor at the stations in Sumner, Puyallup and Auburn where either new parking capacity, local feeder service or both are needed. These are critical to Sound Transit’s continued ability to serve the growing demand.
These issues also highlight the need for a high level of regional cooperation and decision making
among Sound Transit, local transit agencies and local governments. While a great deal of
voluntary coordination takes place among the parties, it may not be enough and may tend to
avoid some of the most sensitive issues affecting cost-effectiveness in use of resources and who
pays for which services.

Construction and Planning Environment. As we have reported in the past several years, Link and other capital projects encountered various obstacles related to the very tight construction
market in the region. The bid climate, the skilled labor shortages and the rising prices of
materials again took a toll on budgets and schedules. Numerous projects received bids higherthan the engineer’s estimates and schedules have slipped on both Link and REX construction contracts. Other projects, in particular the Pierce County Sounder track and signal projects are behind schedule in the engineering phases due to delays in reaching agreement on a preferred alternative or for other reasons.

Transit Operating Costs. We have reported repeatedly on the unsustainable growth inoperating costs of Sound Transit’s bus service. This year we are also reporting a concern about a worrisome spike of 10% in the Tacoma Link operating costs from 2006 to 2007. Tacoma Link is operated entirely by Sound Transit and the number of hours of service provided was flat, so this increase is of special concern. For ST Express, 2007 again saw an increase of 10% in the net-operating expense and about 6% in the cost per hour of service, for the third year in a row. A much higher increase is projected in 2008. The most recent estimates indicate a 2008 rate of $129.35 per full Sound Transit platform hour. This cost is up 13.6% over 2007, based on preliminary year-end figures. This increase is affected by a one-time payment of $3 million to King County for the use of the Downtown Seattle Transit Tunnel. If the $3 M is taken out of the calculation, the hourly cost is projected to be $124.42, still an increase of 9.2%. Staff believe that these estimates are conservative, nevertheless, this growth rate becomes a concern when compared to the 5% cost growth that Sound Transit continues to assume for future year planning purposes.

Transition from Capital to Operations. Over the years, COP has highlighted areas for
improvement at Sound Transit. As the agency draws closer to beginning service for Central
Link, we would draw the Board’s attention to an area that has great potential for surprises: the transition from capital project to operations. The recent computer software hiccup in the
downtown transit tunnel is an example of a type of problem we hope will not recur. We are concerned about the complexity of coordination and communication created by the fact that operation is contracted to King County Metro and is not entirely in Sound Transit’s control. Metro’s staffing plan is behind schedule and there appear to be continuing extended negotiations taking place about what appropriate staffing levels should be. We urge the Board to carefully monitor the rail activation planning that is taking place.

These challenges do not detract from the successes. Sound Transit is a thriving organization with strong leadership and management. As we have stated in the past, we urge regional and state policymakers, as they grapple with our regional transportation governance, to “do no harm.” Sound Transit has continued to grow in effectiveness and accumulated skill in recent years, and it is critical that we refrain from any changes in governance that could harm the strengths that Sound Transit has developed.

Review of Agency-Wide Activities
In addition to its major programs of designing and building capital projects and providing transit services, Sound Transit plans, coordinates and manages various regional activities and
supporting programs.

ST2 and Proposition 1. In 2007 a very significant agency effort was expended on the planning and adoption of ST2, followed by public information, outreach and communication activities, coordinated with the Regional Transportation Investment District (RTID). Sound Transit put forth its best efforts to meet what it believed was the public’s desire for a balanced plan that provided benefits to each part of the region. In the aftermath of the ballot measure’s failure, polling indicated that the joint roads and transit proposal was too large, too complicated and unconvincing as the best solution for our region’s transportation problems.

Environmentalists argued that Proposition 1 did not do enough to address greenhouse gas emissions and climate change. Others believed that not all elements of the plan were cost effective investments. Surveys also indicated that despite its best efforts, Sound Transit still needs to win back full public confidence and that some voters wanted to see light rail in service before approving further taxes for system expansion. COP has observed that in response to these findings, the agency is hard at work developing new options for consideration. We look forward to the Board’s discussions. In the meantime, we have formed a COP task force to delve into our own study of high-capacity transit (HCT) planning in the region.

State of the Agency. The agency received positive feedback from several external reviews of its work in 2007. The Federal Transit Administration conducted one of its regular triennial reviews and 21 of 22 areas examined were found to be in good order. (The single area of deficiency was facilities maintenance which the agency has since strengthened with new staff and a new
facilities maintenance plan.)

Sound Transit’s independent financial audit and the state compliance audit were completely
clean and without findings, as was the annual review of adherence to subarea equity procedures.
The State Auditor’s performance audit of Link made a variety of recommendations that were
largely based on events and issues several years old and that had been identified in previous
performance audits. As required by law, management is providing a response and action plan to those findings.

Sound Transit’s professionalism and technical capacity continue to be strong. Despite the
uncertainty about long-term job security, staff turnover for 2007 was at about 18%, just a bit
higher than 2006. Link has largely been able to retain its core technical staff as management is
transitioning its capacity from the Initial Segment to Airport Link and University Link. A
number of other Sound Transit departments lost staff as projects wound down and as competing
organizations recruited from the agency. Senior management says it is not yet concerned about a brain drain but is proceeding cautiously in filling vacancies. Maintaining the positive personnel
environment at Sound Transit speaks very well of the superior executive leadership at the agency and the dedication of staff.

Smart Card. One commitment made in Sound Move that has unfortunately been delayed beyond anyone’s expectation is the integrated regional fare system. Smart Card has been in development among seven transit agencies for a decade and has experienced a variety of challenges. Integrating seven different fare structures is a prime example of the region’s complexity and has proven to be immensely difficult, as has the need to address security and privacy issues. Consultant project management issues have also plagued the project.
Nevertheless, the Smart Card project has now completed its beta test phase and is undergoing
design changes based on what was learned during that process. The electronic card reading
equipment is being installed on the region’s buses and at train and ferry facilities. While Smart
Card implementation has been seriously delayed, management states that it is now on track for
final rollout of the new system by the end of 2008 with full public use in early 2009.
Continuous Improvement. Last year we reported that the agency unveiled a Lessons Learned
program and a performance management system that represented the next stage of agency
commitment to a continuous quality improvement philosophy. These programs have taken a
while to get off the ground and COP will continue to monitor progress with interest as our
members believe these programs are a vital tool in continuing to build public confidence in the
agency. COP recently formed a Lessons Learned task force to examine how well individual
project lessons are being disseminated agency-wide and we will report to the Board on what we
observe.

Sustainability Initiative. In 2007 the Board directed and the agency began to implement a far-
reaching environmental initiative that is addressing fuel and water conservation, energy
efficiency, greenhouse gas emissions, toxics reduction, ecosystem mitigation, procurement of
sustainable products, pollution prevention, and recycling, among numerous areas. Just recently
Sound Transit was awarded the ISO 14001 certification in recognition of these efforts, an honor
for which COP members congratulate the agency. We did note that, as a capital projects agency,
the success of this sustainability program will depend on the involvement of the construction
industry. We encourage Sound Transit to use contract language and incentives that will reward
contractors who are making efforts to work in an environmentally sustainable manner.

Management and Delivery of the Capital Program

As noted above in our summary, Sound Transit continued to make good progress in delivering the Sound Move capital program. Individual projects continue to be challenged by various
obstacles in the regional environment and continue to be met by strong efforts by Sound Transit to manage in this context.

Link Light Rail
Central Link Initial Segment. 2007 represented the high mark in Central Link construction
with most of the $400 million in budgeted spending for the year achieved as planned. At year-
end, the Link Initial Segment was 85% complete and progress was clearly visible along the entire
corridor. All construction contracts have been awarded except for the Southcenter Boulevard
improvements and the Tukwila Station Park and Ride expansion which was authorized for
contract award in January 2008. While the project is 85% complete, only 67% of the
construction contingency has been committed. Outstanding claims will almost certainly use up
additional contingency funds, but the $128 million program reserve is not expected to be needed.
The schedule has moved from an original six months of float to just nine days, however, this
remaining float has been holding steady for the past five months. The excavation of the Beacon Hill tunnel main shaft represents the critical path and the contractor has been maintaining the schedule. Management has stated that it is highly confident that the July 2009 service date will hold. However, if the nine-day schedule float slips any further, the agency and the Board will need to lower public expectations soon about a delayed beginning of service.
Following are some of the highlights of last year’s progress:

• On Pine Street in downtown Seattle, the surface street repaving is complete. The transit
tunnel conversion was completed on time and the tunnel reopened for bus service in
September.
• The Link Operation & Maintenance Facility at Forest Street in SODO is complete and
King County Metro, the contracted operator, has moved into the building. Fully
assembled light rail vehicles have been arriving on site.
• At the Beacon Hill tunnel, the tunnel boring machine broke through the east portal on the
southbound tunnel bore but did not complete the northbound bore by year-end as had
been scheduled. The project had to be shut down for a month due to a fatal accident on
site; also the contractor has not kept pace with the planned production rates. The
schedule slip on this segment is critical and Sound Transit has continued to work with the
contractor to try to make up the delay. The excavation of the Beacon Hill station is
complete. At the east end of the tunnel, the McClellan Station is progressing well with
structural steel and roofing complete. The aerial guideways on the east and west ends of
the tunnel are 99% complete.
• In the Rainier Valley, the repaving of Martin Luther King Jr. Way South has been
completed and the new streetscape with sidewalks and landscaping is pleasing to the eye. Track is being laid along the corridor and three stations are under construction (Columbia City, Othello and Rainier Beach) with completion due in the first quarter of 2008.
• In Tukwila, the 2,200 precast concrete segments of guideway are all in place and the
gantry was dismantled and moved on to its next project. The Tukwila International
Boulevard Station was completed and is in the process of being commissioned.

As is to be expected on any large construction project, there have been a variety of issues to
manage. Due to the project delays, the follow-on systems contractors have had to begin work on many sites while the civil contractors are still there. This has led to significant coordination
challenges. Disagreements between the agency and some of its contractors have led to
unresolved claims, one of which is currently in mediation. The challenge to consistently manage erosion control in some locations led to Department of Ecology fines. Sound Transit leadership and construction management staff are managing these issues closely and COP believes that there is openness in the reporting of these issues to the Board.


Airport Link. Sound Transit’s guideway and trackwork contract at the north end of the Airport is proceeding on schedule, however, the Port of Seattle’s contract to build parts of the guideway and relocate airport roadways has slipped. The critical path challenge is the Airport Station
which was split into two contracts after the sole bidder came in at almost twice the engineer’s
estimate. The station structural elements were awarded and are under construction. The station finishes have undergone value engineering and redesign and are scheduled to go to construction this year. Staff have stated that with careful coordination the December 2009 service date for
Airport Link will still be met.

University Link. While construction is proceeding on the Initial Segment and Airport Link,
University Link also made good progress in 2007. Engineering is moving forward, with the
tunnel contracts at 60% design and the Capitol Hill and Husky Stadium stations at 30% design
levels. In 2007, the Sound Transit-University of Washington master agreement was finally
signed after many years of difficult negotiations. Critical tasks going forward include the
submittal of the full funding grant agreement (FFGA) to the federal government and obtaining
Congressional approval of the $750 million grant; proceeding with right-of-way acquisition of
243 parcels and 138 business and residential relocations; and groundbreaking in the fourth
quarter of 2008.

Sounder
The Sounder capital program is 80% complete. On the Everett-Seattle Sounder commuter rail
segment, Sound Transit is responsible for regulatory permits, environmental mitigation, and the
construction of stations and a layover facility to store trains. The fourth and final easement was
acquired from Burlington Northern Sante Fe Railroad (BNSF) this year, providing the right to
run trains on the corridor in perpetuity. The first phase of constructing additional layover track
at Everett Station was completed, allowing the 3rd train to begin service in September 2007. The Mukilteo Station (north platform) is under construction and train service to Mukilteo will begin in 2008. The Everett station phase 2 has experienced difficulties with property acquisition and the Mukilteo (south platform) and Edmonds stations continue at schedule and budget risk due to complex funding and coordination issues related to planned Washington State Ferries terminals.

On the Tacoma-Seattle Sounder segment, phase 2 track and signal improvements are nearing completion of capacity improvements that will permit additional trains to be in service by
September 2008. Progress on the phase 2 improvements allowed the 5th and 6th trains to begin service in September 2007. The third phase of remediation at Reservation Connection was
completed in June 2007, establishing embankment stability and allowing that segment to be turned over for normal maintenance.

On the Tacoma-Lakewood segment, both sections are delayed: M Street-Lakewood is waiting to
accommodate WSDOT’s Point Defiance bypass project and D to M Street was delayed while
alternative alignments were analyzed and considered. M Street-Lakewood is now on track to go
to construction in the second quarter of 2008. On the D to M Street segment, the Board in
December selected a preferred alternative that includes a Pacific Street railroad overpass that
puts the project $70 million over budget. Sound Transit has just $25 million for the project and
must work with other parties to secure funds to fill the shortfall. The Lakewood Station is under construction, and the contract was awarded for the South Tacoma Station. .

Regional Express

Sound Transit successfully opened the Canyon Park Freeway Station and the Totem Lake
Freeway Station this year. The very striking Canyon Park project received recognition for its
design from the American Institute of Architects. Also in 2007, five projects began construction: the Totem Lake Transit Center, I-90 Two-Way Transit Stage 1, Bothell Branch Campus Access, SR522 Kenmore and North Everett Transit Center.

Two projects were scheduled for service in 2007 but were delayed: the Mercer Island Park and Ride and the Totem Lake Freeway Station. The Mercer Island Park and Ride experienced
consultant design errors resulting in almost a year’s delay and $2 million in increased cost. The Totem Lake Freeway Station experienced design errors by WSDOT that necessitated demolition and rebuilding part of the structure, leading to a $6 million cost overrun. The State Legislature is expected to authorize the $6 million to repay Sound Transit.

Schedule and budget risks continue for the Mountlake Terrace Freeway Station, I-90 Two-Way
Transit Stages 2 and 3, and the Renton HOV Access project. Mountlake Terrace has expanded
to cost more than is available in Sound Transit’s budget. Staff are trying value engineering and
scope reductions to reduce the cost. For I-90 Stages 2 and 3, Sound Transit has funded its share
of the projects but WSDOT’s share is partially funded (Stage 2) and unfunded (Stage 3).
Funding needs to be authorized for these projects as they are expected to provide capacity that is needed before work on the 520 bridge can begin. The Renton HOV project is on hold at 30%
design pending funding of WSDOT improvements on I-405 that must be completed first.
Ten projects are being implemented by third parties with capped contributions from Sound
Transit. These projects are all in various stages of design under the lead of the Cities of Everett,
Bothell, Kenmore, Redmond, Kirkland and Renton as well as Evergreen Health Care and King
County Metro. While Sound Transit’s contributions to these projects are capped by agreement,
some of these projects are behind schedule and over budget, and in a few cases local agencies are
asking Sound Transit to share in the increases. We urge the Board to stand firm on the terms of
the agreements. COP believes that Sound Transit should draft more stringent performance-based agreements in the future so that taxpayers do not end up contributing to unrealistic or poorly managed projects.


Transit Operations
Sound Transit operated four transit programs in 2007: Tacoma Link, Sounder, ST Express and
Accessible Services. Planning is actively underway for beginning service on Link light rail
between Downtown Seattle and Tukwila in July 2009, with service scheduled to be added to Sea- Tac Airport by December 2009. Transit services offered by Sound Transit again made very
positive gains in 2007 with ridership growing substantially on the two largest programs, Soundercommuter rail and ST Express bus. Despite the strong growth, Sound Transit’s ridership levels have not yet reached the original Sound Move forecasts.

Boardings on ST Express bus were up 10% (after growth of 11% last year). Weekday bus
boardings in the 4th quarter of 2007 stood at 37,000, compared to the 54,000 projected for 2010 in Sound Move. The strongest gains in riders occurred on the corridors connecting the region’s major urban centers, Everett-Seattle, Redmond-Seattle, Bellevue-Seattle and Tacoma-Seattle. On Sounder commuter rail, ridership was up 27% (on top of last year’s 42% growth), with the south corridor from Tacoma-Seattle representing by far the stronger market. Weekday boardings on the commuter rail service were at 8,800 in the 4th quarter, compared to the 2010 Sound Move forecast of 12,600. Tacoma Link ridership grew at a modest 4% in 2007.
ST Express. As noted in the summary section of this report, despite the strong demand, Sound
Transit is constrained for a variety of reasons in its ability to add service. The ST Express
service is limited by a lack of additional bus and maintenance base capacity and by steep growth
in costs. Route 511 Ash Way-Seattle and route 565 Federal Way-Overlake with 12 weekday
peak period trips each are at 100% (standing room only) capacity. Other routes are close behind.
The agency was able to add just 4% more hours of service in 2007. Also, the reliability of ST
Express is highly dependent on the capacity of the HOV system and the state’s willingness to
manage it.

We have reported repeatedly on the worrisome growth in operating costs of Sound Transit’s bus service. For the past three years, net operating costs have grown 10% per year and the costs per hour of service have grown at about 6% per year. Next year’s growth is budgeted to be even higher. These growth rates are unsustainable when compared to the 5% cost growth that Sound Transit continues to assume for future year planning purposes.

ST Express bus service is based on a negotiated rate per hour of purchased transportation with
the three local transit agency partners, King County Metro, Pierce Transit and Community
Transit, plus Sound Transit’s own overhead costs. The current 2008 forecast indicates a blended
rate of $129.35 per full Sound Transit platform hour (total time buses are in operation, including
time driving to and from the base and layovers between trips). This cost growth is up 13.6%
over 2007, due to a scheduled one-time payment of $3 million to King County Metro for debt
service on the downtown transit tunnel, but also due to rapid growth of partner hourly costs. If
the $3 M is taken out of the calculation, the hourly cost grows to $124.42, still an increase of
9.2%. These figures are changed from the published draft 2008 budget because of ongoing
partner negotiations over costs for 2008 and the incomplete reconciliation process for 2007.
This year’s cost growth is based on a 2008 platform hour of $115.90 (up 6.1%) at King County Metro, $93.45 (up 8.2%) at Community Transit, and $99.06 (up just 1.6%) at Pierce Transit.
Even with the strong growth in ridership, Sound Transit’s ST Express cost per boarding has been flat for the past three years.

Despite the concerns COP has over the ST Express operating costs, we were pleased to note that
some indicators are trending positive. As a result of strong bus ridership, the cost per boarding
has been flat at $6.50 for the past three years. The efficiency in bus operation has also improved,
as the ratio of revenue hours to total hours operated has steadily declined and in 2007 only 20% of hours were not carrying passengers (down from one-third a few years ago).

Sounder. For Sounder commuter rail service, costs per hour and per boarding are coming down because of the very strong growth in ridership and the nature of the cost structure negotiated with BNSF. The 2007 cost per revenue hour declined by 9% to $1,282.18, after declining 5% the previous year. The cost per boarding dropped 14.5% to $11.47. This was the fourth year in a row that this indicator showed a decline.

Sounder is projecting significant growth of 48% in trips operated in 2008 due to the agreement
with BNSF to add trains next year. While total costs will rise as service is added, the cost per
hour is projected to decline by 13% to $1,112. 68. It remains to be seen whether constraints in
parking capacity and feeder service on the south corridor will dampen the strong ridership
growth.

Tacoma Link. The Tacoma light rail service is operated by Sound Transit directly, unlike the
bus and commuter rail services which are contracted to other agencies. While operating hours of service remained flat in 2007, the operating costs went up 10% after only a modest increase the previous year. The cost per boarding was up 6% to $3.48. While Tacoma Link has a relatively small budget compared to the other services, the steep increase is a concern especially as this service is largely in Sound Transit’s control.

Over all, these operating statistics indicate that Sounder is in an excellent position with respect to its cost and productivity trends, however, Tacoma Link costs rose at an alarming rate in 2007 and ST Express continued to present ongoing challenges for the agency. We urge the Board to
monitor operating cost growth from year to year and ensure that staff are making realistic
assumptions about future increases. As COP has recommended in the past, we also recommend for ST Express that the Board consider other operating models than the current sole source
contracting arrangement with the three local providers. The expiration in 2009 of the current
contracts presents an opportunity to improve on the current situation and to obtain greater
certainty of costs and better control over cost growth.

The articles are posted solely for educational purposes to raise awareness of transportation issues. I claim no authorship, nor do I profit from this website. Where known, all original authors and/or source publisher have been noted in the post. As this is a knowledge base, rather than a blog, I have reproduced the articles in full to allow for complete reader understanding and allow for comprehensive text searching...see custom google search engine at the top of the page. If you have concerns about the inclusion of a specific article, please email bbdc1@live.com. for a speedy resolution.